CBAM Registerindependent guide

CBAM default values: Uganda

Uganda has country-specific default values for 27 CBAM products (aluminium, cement). For 5 further products no value is published, so the “other countries” value applies. Source: Annex I, Implementing Regulation (EU) 2025/2621.

Values are tCO₂e per tonne of product. “2026” to “2028+” include the mark-up. The estimated cost per tonne uses the 2026 value, the CBAM benchmark for the indicated production route, the 2026 CBAM factor (97.5 %) and the 2026 Q3 certificate price of €82.32. Run your own figures in the cost calculator.

Cement

CN codeProductDirectIndirectTotal202620272028+Route≈ €/t 2026
2507 00 80Calcined clay other countries––0.2800.3080.3360.364€0
2523 10 00White clinker other countries––1.3701.5071.6441.781B€55
2523 10 00Grey clinker 0.9500.0100.9501.0451.1401.235A€33
2523 21 00White Portland cement other countries––1.4501.5951.7401.885€62
2523 29 00Grey Portland cement 0.9900.0201.0101.1111.2121.313€38
2523 90 00White hydraulic cements other countries––1.4901.6391.7881.937B€67
2523 90 00Grey hydraulic cements 0.9400.0300.9701.0671.1641.261A€34
2523 30 00Aluminous cement other countries––2.0302.2332.4362.639€126

Aluminium

CN codeProductDirectIndirectTotal202620272028+Route≈ €/t 2026
7601Unwrought aluminium 0.360–0.3600.3960.4320.468L€25
7603Aluminium powders and flakes 0.510–0.5100.5610.6120.663L€35
7604 10 10Bars and rods 0.730–0.7300.8030.8760.949L€54
7604 10 90Profiles 0.750–0.7500.8250.9000.975L€56
7604 21 00Hollow profiles 0.750–0.7500.8250.9000.975L€56
7604 29 10Bars and rods 0.730–0.7300.8030.8760.949L€54
7604 29 90Profiles 0.750–0.7500.8250.9000.975L€56
7605Aluminium wire 0.730–0.7300.8030.8760.949L€54
7606Aluminium plates, sheets and strip, of a thickness exceeding 0,2 mm 1.190–1.1901.3091.4281.547L€96
7607Aluminium foil (whether or not printed or backed with paper, paperboard, plastics or similar backing materials) of a thickness (excluding any backing) not exceeding 0,2 mm 1.190–1.1901.3091.4281.547L€87
7608Aluminium tubes and pipes 0.750–0.7500.8250.9000.975L€56
7609 00 00Aluminium tube or pipe fittings (for example, couplings, elbows, sleeves) 0.750–0.7500.8250.9000.975L€56
7610 10 00Doors, windows and their frames and thresholds for doors 0.750–0.7500.8250.9000.975L€56
7610 90Other 0.750–0.7500.8250.9000.975L€56
7610 90 10Bridges and bridge-sections, towers and lattice masts 0.750–0.7500.8250.9000.975L€56
7610 90 90Other 0.750–0.7500.8250.9000.975L€56
7611 00 00Aluminium reservoirs, tanks, vats and similar containers, for any material (other than compressed or liquefied gas), of a capacity exceeding 300 litres, whether or not lined or heat-insulated, but not fitted with mechanical or thermal equipment 1.190–1.1901.3091.4281.547L€87
7612Aluminium casks, drums, cans, boxes and similar containers (including rigid or collapsible tubular containers), for any material (other than compressed or liquefied gas), of a capacity not exceeding 300 litres, whether or not lined or heat-insulated, but not fitted with mechanical or thermal equipment 1.190–1.1901.3091.4281.547L€87
7613 00 00Aluminium containers for compressed or liquefied gas 1.190–1.1901.3091.4281.547L€87
7614Stranded wire, cables, plaited bands and the like, of aluminium, not electrically insulated 0.730–0.7300.8030.8760.949L€54
7616 10 00Nails, tacks, staples (other than those of heading 8305), screws, bolts, nuts, screw hooks, rivets, cotters, cotter pins, washers and similar articles 1.190–1.1901.3091.4281.547L€96
7616 91 00Cloth, grill, netting and fencing, of aluminium wire 1.190–1.1901.3091.4281.547L€96
7616 99 10Cast 0.510–0.5100.5610.6120.663L€35
7616 99 90Other 1.190–1.1901.3091.4281.547L€96

Production routes

The route letter decides which CBAM benchmark is used for the free allocation adjustment when default values apply:

  • A: grey clinker / cement
  • L: secondary aluminium

Notes

  • Indirect emissions count towards the CBAM obligation only for cement and fertilisers. For iron and steel, aluminium and hydrogen only direct emissions are priced.
  • Default values do not need third-party verification. Actual values supplied by the producer must be verified by an accredited verifier.
  • The Commission must review the default values by the end of 2027.

All countriesDefault values vs actual emissions